PROJECT FINANCING IN SOUTH ASIA: A TALE OF TWO POWER PROJECTS

By
SARA MAHBOOB[1]

I.       Background: The Need for Project Financing in South Asia

Countries in South Asia vary immensely in terms of size, wealth, growth, political risk, legal and regulatory frameworks and availability of domestic / offshore funding. But they all need to build large, long term infrastructure assets. Modern Infrastructure, particularly electricity, is critical to economic development. Project finance, otherwise known as limited recourse finance, enables joint ventures to raise focused, risk sharing finance in key industries for these countries; and is the leading method for cash - strapped governments to introduce private sector skills, disciplines and funding for all kinds of infrastructure.[2] The potential business is huge but the practicalities can be challenging.

The financing in such projects generally takes place in two forms: equity and debt capital.[3] The sponsors or developers of the project are usually a group of large investors, both domestic and foreign, that make equity contributions to the project in the range of 20% to 25%.[4] The lenders are generally large international commercial banks and multilateral lending agencies.[5]

Because of the large amount of funding required for infrastructure projects, debt is usually obtained in the form of syndicated loans with the participation of more than one bank.[6]

Unlike other methods of financing projects, project finance is a seamless web that affects all aspects of a projects development and contractual arrangements, and thus the finance cannot be dealt with in isolation. The various parties involved in the project (e.g., project developers, governments and other public authorities, engineers, contractors, equipment suppliers, product off takers, and other parties to the project contracts) need to have understanding of how project finance works, and how their part of the project is linked to and affected by the project finance structure.[7]

Despite the risks and challenges present, South Asia remained one of the worlds fastest- growing regions during the last decades, with particularly strong growth in India. Domestic reforms and external assistance have helped fuel rapid economic growth, which has averaged 6 percent a year since 2000.[8] For a region that is developing swiftly, there is a strong need for the private sector to continue to play a role in facilitating strong and sustainable growth across the region.

According to the World Bank, the need for infrastructure investment in South Asia is enormous: Asian countries which historically have accounted for only 15% of the project finance market will require $2 trillion of infrastructure investment over the next decade to maintain their current rate of economic development.[9]

II.      A Tale of Two Power Projects: The Hub Power Project and Dabhol Power Project

Not all South Asian countries suffer from the same problems, but as a generalisation the region still has the legacy of state owned vertically integrated electricity supply industries, often with the characteristic politicization of tariff setting, high level of non-technical losses, high levels of debt or arrears, high level of manning, and poor commercial performance. As a result, it is difficult for the public sector to finance its investment needs on commercial terms.[10]

Therefore, the government is incapable of publicly funding projects of the required scale and requires private participation in energy development ventures.

This paper analyses two mega power projects in the emerging market economies in South Asia; the Hub Power Project in Pakistan and the Dabhol Power Project in India. The paper will discuss these projects from a legal, business economic and public policy perspective with a special focus on the role of investors, lenders, owners and governmental participants. The main area of focus of this paper is the structuring patterns and the financing patterns of these projects when they were negotiated.[11] Also, a discussion of some of the risks (which were or werent allocated) is also undertaken.

While there are positive aspects of both these projects,[12] this paper presents a discussion focusing more on the gaps and challenges faced to help foreign investors understand the nature of risks and challenges involved when investing in power infrastructure in South Asia. This study will also provide a useful case study for government officials, lawyers and other technocrats who are involved in the negotiations of such projects in future in the host country.[13]

a.  The Hub Power Project in Pakistan

The Hub power project is located on the Arabian Sea coast of Pakistan in the province of Baluchistan and is located at approximately 45 km from Karachi.[14] This project is arguably one of the largest privately financed power project in South East Asia. The site was very unique in that it was in an area where there was no population and no infrastructure.[15]

Hub is important to Pakistan for several reasons. In addition to being the largest private sector project in the country, it demonstrates investor confidence in the expansion of the private sectors role in infrastructure development. The project also played a significant role in the formulation of the Governments long-term strategy to attract private investment to the power sector and the development of independent power contracts. Because of its pioneering nature, the project probably encountered most problems likely to face a private infrastructure project in a developing country, thus the solutions developed and the lessons learnt provide an interesting case study for future investors and other project participants.

The process of setting up the project began when Pakistan Government first declared a policy of privatization of its power plant development in 1985. In response to Government of Pakistans (GOP) request in 1987 for Private Sector proposals to design, finance, construct, own and operate power plants to supply the national grid, 20 proposals were submitted, ranging in capacity between 2MW and 600 MW. Of these, Xenel Industries of Saudi Arabia and Hawker Siddeley Power Engineering of the United Kingdom proposed a construction of two power stations of 600 MW each to supply power to Water and Power Development Authority[16] (WAPDA).[17]

Several sites were examined in terms of efficiency of fuel supply, ease of interconnection with the national transmission network, and environmental considerations. The site at the mouth of the Hub River in Baluchistan on the Arabian Sea was selected as fuel could easily be delivered to the power plant by barges or a pipeline, and linkage with WAPDA transmission network was possible by cutting eastwards across Baluchistans virtually uninhabited desert and connecting with WAPDAs network near Jamshoro in Sindh Province.[18]

At this point, Xenel and Hawker Siddeley saw the merits of combining forces as sponsors and investors (SI) to: capture the economies in sharing infrastructural facilities such as fuel and water supply systems and achieve better coordination in negotiating with the GOP. In order to ensure that the site for the Complex would meet environmental standards, an environmental screening study was undertaken by KBN Engineering and Applied Sciences Inc. of the U.S., under financing from USAID. The study found environmental conditions at the site appropriate for the siting of an oil-fired power plant of about 1,300 MW.[19] In addition, the environmental screening study outlined a program for the installation of monitoring equipment for compiling data on ground and air pollution to provide the basis for the design of the Complex in compliance with environmental guidelines of GOP, the Bank and Private Sector Energy Development Fund (PSEDF).[20] The agreement between SI and GOP on the tariff for the sale of electricity to WAPDA allowed covering possible increases in capital cost attributable to changes in plant design to comply with the recommendations of the ongoing environmental study. The cost of these changes, if any, would be automatically reflected in the tariff.[21]

i)   Structuring of the Project

In accordance with the minimum functional specifications for the Complex, agreed by SI and WAPDA, a consortium led by Mitsui Co. of Japan was selected by SI for the implementation of the Complex from among four major international companies who quoted for the construction of the Complex. Mitsui & Co. was selected on account of various reasons including its competitive price and its good performance in constructing a 600 MW coal-fired power station in China.[22]

Mitsui & Co. put together a consortium of equipment suppliers and contractors, to participate in the construction of the power station within the parameters agreed by SI and GOP. The construction consortium entered into a lump sum fixed price for the design and construction of the Complex which would provide for the commissioning of the plant in accordance with a timetable and penalties for delay or failure of performance. All members of the construction consortium took several and joint liabilities, contributing towards project development and provided equity. SI selected British Electricity International (BEI) of the U.K, and Canadian Utilities Power (CUP) of Canada, for the operations and maintenance of the Complex. BEI and CUP also contributed to the development costs and agreed to provide equity.[23] SI, Mitsui & Co., along with the rest of the Construction Consortium, BEI and CUP, formed the Hub Power Group (HPG) to develop the project and negotiate further agreements.[24]All obligations negotiated by HPG were assumed by the Hub Power Company (HUBCO) once it was incorporated and staffed in Pakistan. The expenditures of HPG were capitalized as part of the equity of HUBCO.[25]

Under limited recourse project financing, lenders usually require the earmarking of a fund to meet contingencies not anticipated at the time the fixed price turnkey contract[26] is signed. The fund is intended to ensure that delays, if any, due to unforeseen events are expeditiously addressed to minimize the adverse impact on the forecast project revenues. In the present case, a reserve contingency fund of US $150 million had been included in the overall estimate of the cost to cover increases in costs during construction.

ii)  Financing of the Project

The financing of the project was largely achieved due to the comprehensive set of contractual agreements containing the necessary security that would ensure the viability of the project in the coming years. The major shareholders of HUBCO were Xenel Industries Ltd., National Power Energy, Commonwealth Development Corporation, IHI,[27] Mitsui and K&M Engineering. The debt was financed in two forms with major provisions from a World Bank organized fund (PSEDF) and other debt provided from Japanese, Italian, French export credit agencies and the Commonwealth Development Corporation (CDC).[28]

In addition to the support from the World Bank and other governmental and multilateral sources, including the governments of France, Italy, Japan, the United Kingdom and the United States under the Pakistan Energy Development Fund, the World Bank and the Import/Export Bank of Japan jointly developed an Expanded Co-financing Operations Program to assist the international commercial debt funding by provisions of a partial guarantee.

A significant portion of the offshore debt was also guaranteed by certain export credit agencies. Rupee debt was provided by a group of local banks led by the National Development Finance Corporation of Pakistan.[29] The amount of debt financing required for the project necessitated that it be raised from a variety of sources. Other large private sector infrastructure projects will likewise be obliged to obtain debt financing from many different sources, given the exposure limitations of lenders, insurers and guarantors.[30]

A total financing of US$ 1.8 billion included US$ 1.7 billion equivalent in foreign exchange and about US$ 100 million equivalent in local costs. The capital structure was 20% equity and 80% debt[31] – the debt was mobilized on a project finance basis. Included in the financing plan were costs associated with the turnkey construction contract, development costs, interest during construction and other finance related costs, as well as a reserve contingency fund.

The Power Purchase Agreement (PPA) secures the projects revenue streams and is the most important commercial agreement in such projects. This 30-year agreement in current case also defined the interface between HUBCO and WAPDA. Fuel Supply was secured through this 30 year agreement between the Government owned fuel supplier, Pakistan State Oil Company, and HUBCO. An Operation and Maintenance Agreement (OMA) between HUBCO and National Power International (a subsidiary of National Power, UK) had an initial term of 12 years and provides for operation and maintenance of the plant according to agreed terms and technical criteria.

Several other agreements/provisions were integral components of the contractual arrangements of the project. These included: i) escrow agreements[32] for local and offshore escrow accounts; ii) foreign exchange risk insurance provided by the State Bank of Pakistan for a fee included in the project cost; and iii) a shareholders agreement and related corporate documentation.[33]

iii) Corruption Allegations and Renegotiations

In Pakistan, during this time, the basis on which independent power projects like these were selected and accorded attention was not transparent and subject to political influence which led to perceptions of corruption.[34] Rather than proceeding through competitive bidding for private power, Pakistan instead set a tariff ceiling for investors. When corruption was alleged in some of the sub-projects (especially HUBCO), the Bank initially found it difficult to respond given its multiple roles (i.e., advisor to the Government, lender to WAPDA, indirect lender to Independent Power Projects through the LTCF, and guarantor to commercial lenders through the partial risk guarantees). Bank practice would dictate that the Bank not get involved in commercial disputes; however, the Bank had a responsibility to act once the partial risk guarantees were under threat.[35]

Initially, the Bank had advised the Government to separate the commercial and criminal issues in an attempt to bring the perception of an orderly framework to resolving the Independent Power Projects (IPPs) disputes. WAPDA was facing severe cash flow problems and was not in a position to honor its payment obligations under the PPAs. In addition, the country's foreign exchange reserves were dangerously low which jeopardized the Government's obligation under the Implementation Agreements to convert rupees into foreign exchange. Some IPPs indicated a willingness to renegotiate in recognition of the country's difficulties. However, separating the commercial and corruption issues proved difficult to do in practice in the case of HUBCO, where the Government/WAPDA was of the view that the original commercial terms were fraudulently obtained. Ultimately, both HUBCO and the Government/WAPDA requested the Bank to act as a facilitator in resolving the dispute since attempts by the parties to renegotiate the commercial terms were continuously bogged down in corruption allegations and refutations. In light of this, the lesson learnt for such projects is that governments and governmental agencies should be encouraged to pursue corruption strictly according to law and internationally recognized due process, and in the meantime contractual obligations should be honored.[36]

Renegotiating concession agreements is not unusual in the private sector, particularly when prevailing conditions substantially change (e.g. external macro shocks). However, negotiations will more likely result in mutually acceptable solutions when they occur in a commercial atmosphere, free of coercion. Particularly, in the context of future IPP solicitations, it may be useful to set out the principles of how the benefits or burdens of future debt refinancing or restructuring should be shared among the parties involved. Including such principles in future PPAs could: (a) facilitate the restructuring of debts in jeopardy situations, and/or (b) encourage IPPs to refinance debt in the event interest rates fall substantially and refinancing could lead to significantly lower cost of debt to the benefit of the both the IPPs and the host country. Not having had at the outset such “rules of the game” could be one of the reasons for the few incidents of debt refinancing or restructuring among the Pakistan IPPs.[37]

b.  The Dabhol Power Project in India

In 1991, as part of Indias liberalization efforts, the power sector was identified as one of the key infrastructure sectors to be developed to spur economic growth in the country. While the Government of Indias (GoI) intent was to liberalize the entire sector, the generation sector was opened up first, since it was felt that this sector was more amenable to private sector participation. In 1992, pursuing this intent of economic liberalization, the Congress led GoI under then Prime Minister P V Narasimha Rao, announced it would open up the power electricity sector to foreign investment.

In turning to private investment for power plant development, the GoI gave the first few private sector projects the status of pioneer projects, or “fast track” projects.[38] For these fast track projects, eight of which were eventually signed, the standard public tendering process was not followed because the Indian Government was sensitive to its weak negotiating position.[39]

Instead, the Central Government negotiated with the IPPs for individual projects in order to entice them to invest in India by taking measure to reduce their financial risk.[40]

Enron had begun to investigate opportunities in the Indian power sector in 1992, when India opened its power sector doors to private foreign investors. In May of that year, Enron executives pitched their ideas to the Indian power secretary. By June 1992, Enron had selected Dabhol as the site for a project. Following their survey, they met with the representatives of the government of Maharashtra and on June 20 1992, a Memorandum of Understanding (MoU) with the state government was signed and with General Electric.[41]

i)   Structuring of the Project

From the projects inception, Enron strongly promoted Dabhol as a key element of its international strategy. The Dabhol project was easily Enrons most significant overseas endeavor in its size, cost, and political visibility. According to Enron, the 2, 184 megawatt Dabhol plant is the largest gas-fired power plant in the world.[42]

Interestingly, when the World Bank evaluated the Dabhol project it concluded that the project was “not economically viable, and this could not be financed by the Bank.”[43] The World Bank found that the proposed plant would produce too much power at too high a price for the state. Specifically, the World Bank found that the project was too large for base load operation in Maharashtra. The World Bank also found that “the project is not part of the least coal sequence for Maharashtra power development. Local coal and gas are the preferred choices for case load generation.”[44]

According to media accounts, “Indias Planning Commission originally opposed the project on grounds that the plants annual requirement of 3 million tons of gas would drain at least $250 million from Indias foreign exchange reserves.”[45] While the size of the project was scaled down from the originally proposed 2,550 megawatts to a still massive 2,184 megawatts, it is not clear whether this reduction fully resolved the concern about the projects effect on foreign exchange reserves.[46]

The Dabhol project was envisaged as an integrated energy complex comprising a power station, constructed in 2 phases, and an LNG re-gasification plant. The operating entity was the Dabhol Power Company (DPC),[47] which was a joint venture. During most of the project development period, Enron owned 80% of the project, while General Electric and Bechtel each owned 10%. In late 1998, MSEB purchased part of Enrons equity stake, which dropped Enron shares to 65%.[48]

While the project company (DPC) had numerous contracts with various counterparties for construction, financing and operation of the project, the key contract was the power purchase agreement (PPA). Under the PPA, dated December 8, 1993, the MSEB was responsible for making capacity and energy payments to DPC.[49] The GoM subsequently issued a guaranty, pursuant to which it guaranteed MSEBs payments obligations under the PPA.[50] The GoM and the DPC also entered into State Support Agreements whereby the GoM promised, among other things, to promote and support the Dabhol project, including its power over other governmental entities to facilitate the permitting process.[51]

MSEB was the sole customer for DPC, with which it had a 20 yr. (extendable) power purchase agreement (PPA). The tariff structure for DPC was very different to the tariff structure of most other Indian IPPs. While most IPPs had a “cost plus” structure, which provided compensation for operating costs, fuel costs and debt servicing plus a fixed return on equity, DPC had proposed a levelized tariff structure over the life of the PPA in dollar terms. Further, the contract provided for significant penalties on DPC, if it failed to achieve the target availability levels.

ii)  Financing of the Project

The parties negotiated the project terms over an 18-month period, which culminated in the Dabhol Power Company and MSEB signing a power purchase agreement in December 1993. Over the next year, Enron developed the project financing, obtaining US$635 million in financing, insurance, and loan agreements from Bank of America, ABN Amro, a group of Indian banks, the U.S. Export-Import Bank, and the Overseas Private Investment Corporation (OPIC).[52] The main lender group for the project were the domestic lenders (IDBI, ICICI, SBI, IFCI & Canara Bank), export credit agencies (J-Exim/MITI, OND of Belgium, US Exim), OPIC and a consortium of foreign commercial lenders (led by ABN AMRO, Citibank, ANZ Grindlays, Bank of America).

The sponsors were looking to develop the project with non-recourse funding, limiting their liability towards the project to their equity investments and other guarantees that they provided. The fact that the project had only one customer with a weak credit quality, implied that the financing of the project was critically dependent on the credit support mechanism for the project.

In view of this, a multi-layered credit support mechanism was established for both monthly bill payments and termination related payments of the project comprising a letter of credit, a guarantee from GoM, a counter-guarantee from GoI and an escrow account consisting of MSEBs cash collections from selected regions. Of these, the GoI counter-guarantee was available as credit support only for obligations related to Phase I, while the cash flows from the escrow account were only available for Phase II related obligations. In setting up the Dabhol power project financing, the lenders were relying heavily on the guarantees furnished by the GoM and the counter-guarantee given by GoI.

iii)     Negative Reaction, Munde Committee and the Revised Agreement

Enrons Dabhol project in Maharashtra state has been a topic of controversy since April 1992 when Houston based Enron was invited to bid for the project as part of Indias economic liberalization drive. This mega project, unfortunately, became the symbol of the struggle against globalization in India. It has generated endless controversy, including protest rallies, environmental and concerns for human rights abuses, Court cases and political skullduggery.[53]

Fueled by growing negative reaction to the Dabhol project, the opposition party won in Maharashtra in 1995. The new government promptly appointed a group, known as the Munde Committee, to review the Dabhol project.[54] The Munde Committee report critiqued both the process by which the project had been developed and the terms of the deal. It found that the initial memorandum of understanding was rushed and “one sided.” The report also condemned the absence of competitive bids and lack of transparency in the process, critiqued subsequent changes to the project design as addressing “only the concerns of Enron,” and found Enron was given undue favors and concessions. The report also found that the capital costs of the project were inflated, that the rates for the power would be much higher than justified, in part because the contract was based on U.S dollars (placing the risk of currency fluctuations on the state), that there were outstanding environmental questions, and that the project would adversely affect the state of Maharashtra.[55]

Based on this evaluation, in August 1995, the state decided to halt construction and cancel the project. In response to the states action, Enron sought US$300 million in compensation, while attempting to convince the Indian government to reverse its decision. The state government countered by filing suit to void the agreement, alleging fraud and misrepresentation.[56] However, negotiations took place between both the parties and while the state dropped its law suit a revised agreement was drawn. The revised agreement expanded Phase I of the project from 695 megawatts to 740 megawatts and committed the state to both Phase I and the 1,320 megawatt phase II portion of the project (under the initial agreement, the state was bound only to the Phase I portion). As the MSEB was still committed to buying 90% of the plants output and covering the risk of currency fluctuations, the expansion increased the financial risk to the state under the revised agreement.[57]

As it turned out, the price of the power from Dabhol was far beyond what consumers in the area will pay or the state could afford. Phase I of the project ran on naptha, but oil prices were apparently higher than projected, and demand had been substantially lower.[58] In addition, the deal was structured to peg the costs of power to the dollar, so the state bore the risk of currency fluctuations. The state was contracted to buy the full output of the plant, but was purchasing only 10%-20% of the plants output from Phase I. The state was obligated nonetheless to pay the plants full fixed costs, which further increased the rates. In 2001, power from Dabhol was four times more expensive than that from domestic power producers.

III.           Lessons Learnt and Looking Ahead

An analysis of both these mega power projects makes it easy to discern some common issues facing such projects in South Asia. The Dabhol Power Plant was Indias largest ever-foreign investment in power sector and The Hub Power Plant was not only the largest IPP by far in Pakistan, but at the time one of the largest in Asia. Both the projects were launched from a clear need for greater power capacity in both countries.

Most of the problems faced by both these projects are typical of projects attempted in a politically unstable and, for foreign investment, unsophisticated environment without proper on ground analysis. India had a long history of opposition to foreign investment; a large and politically strong state sector; virtually no record of privatization; and strong, nationalistic trade unions in both public and private sectors. While the policy of privatization was set at the national level, implementation would be at the state and local level, where political resistance by governments and state owned organizations often proved to be strong in the past.[59] The political challenge should have been anticipated by project participants prior to going ahead with the project. Even though Congress had been in power for a long time, the change had long been anticipated by political analysts.

In Pakistan, an impressive amount of resources for the power sector were mobilized[60] and that helped elicit an enthusiastic buy-in both within and outside the Bank. The Bank promoted measures for sector management and restructuring, as well as public sector policy reforms, which were generally right and timely. The Government, however, failed to have them implemented at the intended pace. While failures in sector reforms did not precipitate the financial crisis of WAPDA, they compounded it, crippled the efficiency of both WAPDA and the Independent Power Producers, and left the sector overly vulnerable to economic downturns.[61]

Due to political instability, a weak legal and economic environment, and infighting amongst project participants due to vested interests, it took nine years of negotiations before financing was arranged and construction was underway in Pakistan. First power was generated from the project only in mid-1996, eleven years from the start of the negotiations.[62] Hence, in future time should be saved by the local authorities by properly clarifying what is required from the project technically and commercially before inviting private sector proposals.

Matching sponsors of the project of this nature to the scale of the project is essential. Keeping the number of project participants – contract counterparties, contractors and co- financers – to a minimum may help in overcoming administrative hurdles and make the whole process more time efficient. An important lesson learnt from Hub Project is that the power purchase agreement tariff should be determined in the same currency as the project funding. Additionally, the project participants should continue to strive for continuity in the advisers who provide specialized expertise to contract counterparties. An important suggestion in such a project with fragmented financing plans is to create a formal co-financiers steering committee, chaired by the Bank, during project development.[63]

In Pakistan, a long time span was spent basically trying to construct a strong project matrix. On BOT[64] principles, that proved very difficult: the risks of undertaking such a large project made near-impossible to finance on a commercial basis, and in the end, ironically, debt financing liability still fell on the Pakistani government. In addition, the government had to guarantee fuel supply and power off take agreements, as well as foreign exchange risks in the concession and power purchase agreements. Furthermore, the government had to take significant equity participation in the project.

The difficulties with projects like Hub Power Project can largely be attributed to its size. To begin with, the Government should have concentrated its efforts on modest-sized, and as a consequence, more easily financeable projects. In addition, rather than proceeding through competitive bidding for private power, Pakistan instead set a tariff ceiling for investors in an effort to accelerate the private power program and reduce transaction costs in order to quickly address the blackout situation facing the country. This was a very successful tactic in attracting foreign investors, but too many projects were approved due to this and the selection process was not considered transparent.

The Dabhol Power Project was mainly financed by the government financial institutions. Similarly, when the project came into controversy, the US governments pressure on Delhi implied a sense of financial responsibility on the Indian governments behalf. For the continuity of the project the central Indian government appeared to retain financial responsibility, while potential financial benefits would accrue only to the private sector sponsor. The problem was principally that of launching such a large project in an environment characterized by the lack of consensus, lack of understanding of BOT principles, and a very opaque project award process which generated suspicion and accusations by the new government of over-pricing by the investors.[65] Estimated plant costs were in fact far higher per unit of capacity than other comparable plants.[66]

As far as the problem of corruption allegations in both projects is concerned, there must be greater enforcement of anti-corruption laws in future, which can include the establishment of an independent agency on combating corruption. Moreover, an integral component of combating corruption in India and Pakistan should involve the adoption of a whistle-blower protection law to protect those who report instances of corruption within their respective organizations.[67] In conjunction with such broad-based measures, there should be an effort to minimize the possibility of corruption at the level of individual transactions by streamlining negotiations and reducing the number of actors involved.[68]


To sum it up, critics generally accused the two mega projects as being poor on detail, agreement with one-sided negotiations, inadequate acknowledgment of political challenges and not achieving the ultimate goals of producing energy efficiently and in a cost effective manner. An investment which ensures that the above criticisms are not raised can ensure that the investment will be secure despite the challenges in this region.

 



[1].      LL.M. (Boston University School of Law), Member of the Lahore Bar Association, Lecturer School of Law and Policy.

[2].      There is no single agreed upon definition of project finance. For various approaches to explain project finance please see: http://www.people.hbs.edu/besty/projfinportal/definition.htm.

[3].      See Nagla Nassar, Project Finance, Public Utilities, and Public Concerns: A Practitioner’s Perspective, 23 Fordham INT’L L.J.60,60(2000).

[4].      Id.

[5].      Id., at 62-63.

[6].      Id., at 63.

[7].      Principles of Project Finance, E.R. Yescombe, Academic Press, 2002 at pg. 1 - 2.

[8].      Annual Report 2009, The International Bank for Reconstruction and Development/The World Bank, at pg. 38.

[9].      Benjamin C. Esty, The Economic Motivations for Using Project Finance, February 14, 2003, at pg. 1.

[10].    See David Newberry, Power Sector Reform, Private Investment and Regional Cooperation, June 2006, at pg. 6.

[11].    It should be noted that there may be certain revisions in the agreements and certain figures (like estimated costs of the projects) down the road. The facts and figures provided in this paper are true for when the agreements were negotiated.

[12].    For example, the Hub Power Project utilized “co-financing” as a successful mechanism of financing in dealing with financial institutes working under Islamic finance. Also, most aspects of the contractual framework have served as a model for the future projects in this region. Considerable investments were made to meet environmental standards and the Hub Project’s model should be followed in this respect. The Project is also assisting with the sustainable community development of 25 local communities in that area.

[13].    A country where a company that is based in another country has business activities.

[14].    Karachi is the largest city, main seaport and the financial capital of Pakistan.

[15].    For more information please visit: http://www.hubpower.com.

[16].    WAPDA, the Pakistan Water and Power Development Authority, was created in 1958 as a Semi-Autonomous Body for the purpose of coordinating and giving a unified direction to the development of schemes in Water and Power Sectors, which were previously being dealt with, by the respective Electricity and Irrigation Department of the Provinces.

[17].    See The World Bank, Pakistan – Expanded Co-financing Operation to the Hub Company , Staff Appraisal Report, Pakistan, Report No. 9004-Pak, October 1991, at pg.10.

[18].    Id., at pg. 11.

[19].    Id., at pg. 11.

[20].    Due to budgetary constraints, boosting power generation capacity sufficiently would not be possible if Pakistani government relied solely on the public sector. As an alternative, it instituted, with support from the World Bank, "The Private Sector Energy Development Fund"(PSEDF) in June, 1988. The objective of this fund is to foster investments in the energy sector by providing long-term financing under favorable terms to private energy development projects.

[21].    Supra note 15, at pg. 11.

[22].    Id., at pg. 11.

[23].    Toshiba, Kumagai and CUP, could not renew the validity of their prices beyond March 31, 1990 and these were later replaced following tender procedures.

[24].    The World Bank, Pakistan – Expanded Co-financing Operation to the Hub Company , Staff Appraisal Report, Pakistan, Report No. 9004-Pak, October 1991, at pg.11 – 12.

[25].    Id., at pg. 12.

[26].    A turnkey contract is a contract for design and construction of a complete project.

[27].    IHI Corporation.

[28].    The World Bank, Project Finance and Guarantees, Co financing and Financial Advisory Services Vice Presidency, Project Finance Group, “World Bank Guarantee Sparks Private Power Investment in Pakistan,” June 1995, at pg. 1 and 2.

[29].    Hubco Company website: http://www.hubpower.com/history.php.

[30].    The World Bank, Project Finance and Guarantees, Co financing and Financial Advisory Services Vice Presidency, Project Finance Group, “World Bank Guarantee Sparks Private Power Investment in Pakistan,” June 1995, at pg. 2.

[31].    Some sources quote “the project was financed on a 25:75 equity debt ratio.”

[32].    Defined as: a) Document that lays down the conditions (or describes the event) upon fulfillment of (or occurrence) of which the escrow agent delivers the asset or document held in trust by him or her to the named second party or beneficiary; b) Document issued by a bank to certify that the securities or other assets listed in it are on deposit with the bank.

[33].    Supra note 30, at pg. 2.

[34].    See: Lessons from the Independent Private Power Experience in Pakistan, Julia M Fraser, Energy and Mining Sector Board Discussion Paper, May 2005 at pg. 7.

[35].    Id., at pg. 14.

[36].    Lessons from the Independent Private Power Experience in Pakistan, Julia M Fraser, Energy and Mining Sector Board Discussion Paper, May 2005 at pg. 15.

[37].    Id., at pg. 15.

[38].    See: Andrew Ink pen, Enron and the Dabhol Power Company 2 (Am. Graduate Sch. Of Int’l Mgmt.,2002).

[39].    Id.

[40].    Id.

[41].    Human Rights Watch, The Enron Corporation: Corporate Complicity in Human Rights Violations, 10 (January 1999).

[42].    High Stakes Showdown; Enron’s Fight Over Power Plant Reverberates Beyond India, New York Times (Mar. 20, 2001).

[43].    Letter from Heinz Vergin, Director of the India Country Department, World Bank to M.S Ahluwalia, Secretary, Department of Economic Affairs, Ministry of Finance.

[44].    Anu Bhasin Et Al., Enron Development Corporation: The Dabhol Power Project in Maharashtra, India (A), 6 (Harvard Bus. Sch. 1996).[hereinafter referred to as “Case Study”].

[45].    India Okays First Private Power Unit: A 1,920 MW Venture by Bechtel/Enron/GE, Independent Power Report (January 15, 1993).

[46].    Committee on Government Reform U.S House of Representatives, Background on Enron’s Dabhol Power Project (February 22, 2002).

[47].    Some sources refer to this entity as the Dabhol Power Corporation.

[48].    Case Study, supra note 44.

[49].    Expropriation Claim of Bank of America, OPIC Memorandum of Determinations 3 (2003), available at http://www.opic.gov/insurance/claims/report/documents/Bank ofAmerica-September30-2003.pdf (hereinafter referred to as “OPIC Memorandum of Determinations.”).

[50].    Id.

[51].    Id.

[52].    Financing for Indian Plant Secured, Houston Chronicle (January 17, 1995).

[53].    Tony Allison, Enron's eight-year power struggle in India. Asia Times (January 18, 2001).

[54].    High Stakes Showdown; Enrons Fight Over Power Plant Reverberates Beyond India, New York Times (Mar. 20, 2001).

[55].    The Munde Committee, Report of the Cabinet Sub-Committee to Review the Dabhol Power Project (1995).

[56].    Committee on Government Reform U.S House of Representatives, Background on Enron’s Dabhol Power Project (February 22, 2002).

[57].    Id and for a detailed discussion on this please see Harvard Business School, Enron Development Corporation: The Dabhol Power Project in Maharashtra, India (C)2 1996.

[58].    Bidding Set for Enrons India Project, Reuters (Jan. 21, 2002).

[59].    For a detailed discussion on this see Paul Handley, BOT Privatization in Asia: Distorted goals and processes (September 1997).

[60].    In 1993, the Pakistan Peoples Party won elections. In 1994, Prime Minister Benazir Bhutto unveiled Power Policy 1994.

[61].    Lessons from the Independent Private Power Experience in Pakistan, Julia M Fraser, Energy and Mining Sector Board Discussion Paper, May 2005 at pg. 7.

[62].    Id.

[63].    For a detailed discussion on this please see Gerrard, Michael. 1997. "Review of the Hub Power Project." Resource Mobilization and Co-financing Discussion Paper 118. World Bank, Project Finance and Guarantees Department, Washington, DC.

[64].    Build-Operate-Transfer (“BOT”) projects: In this type of project, the Project Company never owns the assets used to provide the project services. However, the Project Company constructs the project and has the right to earn revenues from its operation of the project.

[65].    See: Paul Handley, BOT Privatization in Asia: Distorted goals and processes (September 1997).

[66].    Through Southeast Asia in the 1995-96 period, power companies were estimating the cost of a competitive project a US$ 1 million per kw installed capacity. Dabhol’s project cost was 40 percent more.

[67].    While the Supreme Court in India has previously recommended the passage of such legislation, the central government has not been successful to this end.

[68].    Preeti Kundra, Looking Beyond the Dabhol Debacle: Examining its Causes and Understanding its Lessons, Vanderbilt Journal of Transnational Law, Vol 41:907 at pg. 934.